Leighton Avenue Improvement Project Postponed, Open House Set

By Chase Porter May 1, 2024 | 3:48 PM

Lincoln Transportation and Utilities invites residents to an open house Thursday, May 9, regarding the commencement of a multi-phase improvement project on Leighton Avenue. The event will be from 5 to 7 p.m. at the Easterday Recreation Center, 6130 Adams St.

The ‘Lincoln on the Move’ construction project will close portions of Leighton in three separate phases to reduce traffic inconveniences:

  • Phase 1: North 56th to North 63rd streets — was postponed – now begins May 13, scheduled to be completed in fall 2024
  • Phase 2: North 63rd to 70th streets
  • Phase 3: North 48th to 53rd streets

The open house will provide additional information about elements of the project, including:

  • Mill and overlay of existing surfaces and base repairs where required
  • Concrete pavement repair
  • Removal and replacement of asphalt paving
  • Curb and curb ramp replacements
  • Inlet top replacements
  • Installation of a pedestrian crossing Rectangular Rapid Flashing Beacon

Lincoln on the Move is a six-year, quarter-cent sales tax street investment focused on enhancing Lincoln’s street infrastructure that will dedicate an additional $96 million to street projects in Lincoln through 2025.

For more information on the open house, visit lincoln.ne.gov (search: Leighton).